GM schedules 21 week idle of three truck plants
Fort Wayne will shut down for nine weeks over the course of 10 months, from January to October of 2012, while Flint will stop production for seven weeks from June to November, and the Arlington, Texas facility will be quiet from June to December for five weeks. The Mexico plant in Silao will find out its shut-down schedule next year. GM has been stockpiling a 90-day supply of its Silverado and Sierra pickups to make up for the loss of production.